CONCEPTUAL PHASING
-
Phase 1
2019-2021
This phase demolishes the western portion of the Galleria Shopping Centre, to facilitate construction of the new Wallace Emerson Community Centre.YIELDS
571 residential units
2,296 square metres non-residential GFAJune 2020
Mobilization for commencement of Phase 1 of watermain relocation works adjacent to 1245 Dupont St., scheduled to begin June 10th, 2020. -
Phase 2
2022-2025
This phase involves demolishing the existing Wallace Emerson Community Centre, to facilitate the construction of Block 1.YIELDS
535 residential units
13,421 square metres non-residential GFA -
Phase 3
2026-2028
This phase consists of the construction of Blocks 2 and 3, as well as several key privately owned, publicly accessible spaces, including Points Plaza, The Mews, and The Allée.YIELDS
1,057 residential units
8,271 square metres non-residential GFA -
Phase 4
2029-2030
This phase is the final phase, and completes the construction of Block 4.YIELDS
683 residential units (including 150 affordable units)
4,833 square metres non-residential GFA