Over the course of the past few years, through a series of nearly 40 working sessions, meetings, public open houses and review panels, community feedback was considered and reworked to create the Revised Proposal.
Year
-
January 22
First Reimagine Galleria Working Group Meeting -
January 23
First Reimagine Galleria Public Open House -
March 15
Meeting with Local Area Councillor -
March 22
Working session with City’s Planning and Urban Design staff -
Sept 30
Official Plan and Rezoning Application submitted
-
January 18
Meeting with City Planner -
March 23
First City of Toronto Public Open House -
September 28
Meeting with City Legal staff -
October 27
Revised Official Plan and Rezoning Application submitted
-
January 22
Reimagine Galleria Working Group Meeting #1: Project Introduction -
January 23
Reimagine Galleria Public Open House #1: Project Introduction -
February 10
Reimagine Galleria Working Group #2: Parks and Open Spaces -
February 23
Reimagine Galleria Working Group #3: Mobility -
March 7
Reimagine Galleria Working Group #4: Land Uses and Urban Design -
March 15
Meeting with Local Area Councillor -
March 22
Working Session with City’s Planning and Urban Design staff -
April 4
Reimagine Galleria Working Group #5: Vision and Planning Principles -
April 21
Reimagine Galleria Working Group #6: Presentation of Draft Master Plan -
May 7
Reimagine Galleria Public Open House #2: Presentation of Draft Master Plan -
May 25
Meeting with City’s Real Estate Division -
July 5
Presentation to City of Toronto’s Urban Design Review Panel -
September 30
Official Plan and Re-zoning Application Submitted -
October 15
Reimagine Galleria Open House #3: Presentation of Development Application -
November
First Official Plan Amendment and Re-zoning Comments Received by City Staff -
December 12
Meeting with Local Area Councillor
-
January 13
Meeting with Local Area Councillor